    • #10145
      Alejandro BotíaAlejandro Botía
      Participant

      Hi,
      I’m currently making a project for a college subject and I want to assign extra hours to some of the resources in order to it showing in real costs column but I don’t know how to do this. I’ve searched but I haven’t found a way of archieving this. Can any of you help me with this?
      Thanks.

    • #10146
      Alejandro BotíaAlejandro Botía
      Participant

      I’d like to clear some things I should have said in the post:

      Im using desktop version on Windows.
      The way I’m trying to archieve this is by increasing the % of units of the resources in certain tasks. I have an overtime cost for every resource but in the Tasks spreadsheet, the real column updates only using the normal cost.

      For example, if one of the workers’ cost is 14€/h and the overtime is 28€/h, and he works for 8 hours a day in a task that lasts 1 day, the real cost with no overtime should be 112€, which is correct. But if I double his units in that specific task (200%), the expected cost should be 112+28*8=336 because of 8 hours being normal and 8 hours being extra. But the value I get is only 224, which means that all hours are counting as normal and not overtime hours are being taken into account. So I don’t know how to do this really.

      Am I wrong in something or is there another way of archeiving this?
      Thanks.