For my dissertation project I have to make a gantt chart. The summary line for each phase goes right until the end of the project and I cannot find a way to change it so that for example the phase 2 summary line ends when the phase 3 summary line starts. Its done it for the first one and i have no idea how I have done it.
Any help would be appreciated