Home New Forums discussions ProjectLibre Desktop How to display task bar (time line) in Gantt chart view

Viewing 2 reply threads
  • Author
    Posts
    • #5777
      Gio DGio D
      Participant

      Hi all! For some strange reason, I can only see some of the task bars (the red time line) for tasks on my Gantt chart. What am I doing wrong?? I’ve tried everything I can think of to try and view all the red time lines, but I haven’t succeeded 🙁

    • #5785
      Project_LibreProject_Libre
      Keymaster

      The Cloud and also desktop versions have a Filter feature…. if you are filtering for example ( Critical Tasks) it would only show a subset of project tasks that are critical

    • #5793
      Gio DGio D
      Participant

      The filter isn’t on. I can see all tasks and sub-tasks. It just literally won’t show the time line for some tasks and I don’t understand why.

Viewing 2 reply threads