Hi all

I’ve the same issue importing Microsoft Project File : ID are modified, Predecessor/successor also.
And some grouping have also been modified during import …

Any recommendation for importing files from Microsoft Project ? Does it have to be exported from Microsoft Project in a certain format to improve import in ProjectLibre and avoid all these unexpected modifications ?