How manage % of proress • Jonathan Melilli • No comments Home New › Forums › discussions › ProjectLibre Desktop › How manage % of proress Tagged: % of progress This topic has 1 reply, 2 voices, and was last updated 3 weeks, 3 days ago by Project_Libre. Viewing 1 reply thread Author Posts April 9, 2026 at 10:27 am #9795 Jonathan MelilliParticipant Hi, I need support to understand why when I set % of progress on one activity listed in the project, automatically SW change some date of the project. Thanks. April 15, 2026 at 3:58 pm #9923 Project_LibreKeymaster When you enter percent complete on a task… you have started the task so it puts an Actual Start on the task. This will anchor the task to start on that date and can alter the schedule for successors (or predecessors) Author Posts Viewing 1 reply thread You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in If you don’t have an account, sign up here! Log In Ready to experience ProjectLibre Cloud? Request a Cloud Trial →