Resource Views

How to navigate Resource views — Gantt, Spreadsheet, Distribution, RBS — plus capacity colors, material resources, and the User vs Resource difference.

Path: left nav Resources. Submenu of the same enterprise pool: Gantt · Spreadsheet · Distribution · RBS. Capacity colors on the Resource Gantt: white = none · blue <50% · green 50–100% · red >100% · orange >150%.

Detailed guidance: Resources (open path, capacity colors, Teams, Calendars, Edit Resource, Peak Units graphs).

Watch: Resource View.

Resources submenu with Gantt tooltip Resources submenu — Gantt tooltip — from Resource View. Deep dive: Resources.

Material Resources

Type Material appears in the enterprise pool and Assign dialog (Assign Resources video); for material resource details, see Resources.

Summary Table

Feature User Resource
Login Access Yes No
Assigned to Tasks Indirectly (via Resource link) Yes
Has a “Role” Yes (Security/Permissions) No
Has a “Type” N/A Yes (Work, Material, etc.)

Pro Tip: License Management

By maintaining resources that are not users, you can track an unlimited variety of assets and external labor without consuming your user license seats. Only those individuals who need to interact with the software itself require a User account.

Resource Gantt Chart