Portfolio

How the Portfolio view lists and schedules every project you can see, and how to add, import and open one.

Path: left nav Portfolio. When you log in, Portfolio is often your starting point — a shared browser environment for multi-project, multi-user work on the same live data (no emailed project files / version confusion).

Watch: Portfolio View. See also: Creating a New Project · OBS · Manage Access · Dashboard · Adding & opening projects.

Spreadsheet + Portfolio Gantt

Left — portfolio spreadsheet. Each row is a project you have permission to see. Columns include ID, Indicator, Name, Duration, Start / Finish, Budget Status, Schedule Status, % Complete, OBS, cost fields, Benefit, and Risk — with more available through Field Configuration. Sort, drag-and-drop reorder, and color-code projects.

Right — Portfolio Gantt. Each project shows as a summary Gantt bar on a shared timeline so you can see starts, finishes, and overlaps without opening every project.

Portfolio list and Gantt overview Portfolio home — list + summary Gantt — from Portfolio View.

Portfolio spreadsheet columns and status dots Spreadsheet columns and status indicators — from Portfolio View.

Portfolio Gantt timeline Portfolio Gantt timeline — from Portfolio View.

Flat list vs Group by OBS

Toolbar control tooltip: Group projects: flat or by OBS code. Menu: Flat list | Group by OBS. OBS can represent departments, business units, regions, customers, or programs — see Organization & Structures — OBS.

Group projects Flat list or Group by OBS Group projects — Flat list / Group by OBS — from Portfolio View.

Multi-select resource subscreen

Select one or many projects in the spreadsheet to open a bottom resource loading subscreen. Graph metrics include Peak Units, Overallocation, Remaining Availability (also Work, Cumulative Work, Percent Allocation, Cost…). A resource can look fine in one project and overallocated across the portfolio — this view reveals combined demand. See also: Resource Graph · Resource Leveling.

Portfolio Peak Units resource graph Peak Units across selected projects — from Portfolio View.

Portfolio toolbar

Control What it does
+ Add New Project: Blank · AI · Import — Creating a New Project
Undo / Redo Reverse or restore portfolio edits
Manage Access Public vs Restricted; Add User / Add Team — Manage Access
Open Opens the selected project into Project → Gantt
Calendars / Edit Project calendars; Edit tabs Main · Performance · Actuals · Calendar · Risk · Notes
Group / Zoom Flat vs OBS; zoom the portfolio timeline
Export Spreadsheet · PDF · Gantt image; layout Single page / Paginated; Compact / View columns / Choose fields
Colors + Color Rule (demo: OBS = 1 gray; Risk = Very Low light blue)
Field Configuration Show and reorder portfolio columns

New Project Blank AI Import modal + Add → New Project — Blank · AI · Import — from Portfolio View.

Manage Access Public Restricted Manage Access — Public / Restricted — from Portfolio View.

Toolbar Open tooltip Toolbar Open — opens into Gantt — from Portfolio View.

Edit project Main tab Edit project — Main tab — from Portfolio View.

Export modal formats Export — Spreadsheet / PDF / Gantt image — from Portfolio View.

Colors panel with rules Colors — OBS and Risk rules — from Portfolio View.

Field Configuration panel Field Configuration — from Portfolio View.

Alternate Portfolio views

Under Portfolio in the sidebar: default list+Gantt · Spreadsheet · Metrics (dashboard-style widgets — see Dashboard) · OBS/hierarchy view. Select a project to open an editable project details bottom pane.

Portfolio Metrics dashboard widgets Portfolio Metrics view — from Portfolio View.

Selected project details pane Selected-project details pane — from Portfolio View.

Role-based permissions control which projects appear and which tools you can use. Continue with Adding & opening projects for create/import workflows, or open a row and go to Project View.

Portfolio Management: Adding and Opening Projects

The Portfolio View is more than just a list of names—it is your primary functional hub for initializing work and migrating existing data. Two of the most critical functions performed at this level are Adding/Importing projects and Opening them for active management.

Watch: Create New Project Video

Create New Project video preview screen

Adding and Importing Projects

From the Portfolio interface, users with the appropriate Role Permissions can either start a project from scratch or import data from external sources.

1. Creating a New Project

To start fresh, simply locate an empty row in the Portfolio spreadsheet.

  • Click into the row and type your Project Name.

  • Once the name is entered, the project is officially created within the cloud environment.

2. Importing Existing Projects

If you are transitioning from desktop software, ProjectLibre Cloud supports seamless migration. For the full current workflow (New Project → Import, resource mapping, Peak Units), see Importing Desktop Projects. Formats commonly cited include:

  • .pod: ProjectLibre Desktop files.

  • .mpp /.mpx: Microsoft Project files.

  • .xer: Primavera P6 compatible files.

Important: These are standard industry formats, but you should review schedule logic, links, and constraints after import because third-party export quality can vary.


Opening a Project

Active project management occurs within the Project View. To transition from the Portfolio to the workspace:

  1. Select: Highlight the desired project name in the spreadsheet list.

  2. Launch: Click the Open Project icon in the toolbar.

    Open Project toolbar icon

  3. The Result: By default, the system will launch the Gantt Chart view of the selected project.

Visibility & Teams: If a project does not appear in your Portfolio list, your Role may not have permission to view it, or you may not be a member of the Team assigned to that specific project.


Advanced: The Edit Project Dialog

Edit Project icon

While the Portfolio view manages the “container” of the project, the Edit Project dialog (accessible once a project is open) allows you to modify its DNA.

  • Main Tab: Most data here is inherited automatically from your task-level entries once planning begins.

  • Manual Edits: You can use this dialog to rename the project or add high-level Notes.

  • Project Calendar: One of the most important settings found here—use this to define the global working schedule and holidays that will drive your project’s timelines.

Project Calendar setting in the Edit Project dialog

Next Steps

  • For a New Project: You will land on an empty Gantt Chart. Proceed to the Create Tasks section to begin building your WBS.

  • For an Imported Project: Your schedule will appear as defined in your source file. You can immediately begin using the Dashboard or AI features to analyze and optimize the plan.

For more on importing projects, see Importing Desktop Projects.