Creating and Editing Tasks

Now that your project is open, it’s time to build your plan. Start by entering your tasks and their estimated durations directly into the spreadsheet.

Now that your project is open, it’s time to build your plan. Start by entering your tasks and their estimated durations directly into the spreadsheet.

Watch: Create and Edit Tasks Video

Example Task Structure:

Task Name Duration Note
Project Summary Task Auto-calculated Will reflect total duration after subtasks are indented.
Design 10 Days
Development 10 Days
Document 5 Days
Test 10 Days
Product Rollout 0 Days Entering “0” automatically creates a Milestone.

Task list entered in the Gantt spreadsheet, matching the example structure above

Refining Your Tasks

To add more detail, select a task and click the Edit Task icon. A dialog box will appear with several tabs to help you manage specific data points:

  • Main: Adjust basic info like Duration and Percent Complete.

  • Dates: View Start and Finish dates (calculated automatically by the scheduling engine).

  • Tabs for Deep Control:

    • Predecessors: Set dependencies between tasks.

    • Resources: Assign team members.

    • Advanced: Manage Constraints, Deadlines, and specialized Calendars.

    • Notes: Add context or documentation for specific tasks.

    • Baseline/Actuals: Track your original plan against real-world progress.

The Edit Task dialog, opened from the toolbar icon

Edit Task dialog tabs, including Predecessors, Resources, Advanced, Notes and Baseline/Actuals

After tasks exist on the Gantt, link them (Linking Tasks), assign resources, then deepen the plan in Scheduling (task types, effort-driven, calendars, constraints, baselines, and actuals).